Change Management · Q6 of 7

What's your approach to phased rollouts vs. big-bang changes?

Why This Is Asked

Interviewers want to see your judgment on risk and delivery strategy—when to phase changes for safety vs. when a coordinated cutover makes sense. They're assessing your ability to weigh trade-offs and choose the right approach for the context.

Key Points to Cover

  • When you prefer phased (reduced risk, learn and adapt, rollback easier)
  • When big-bang might be necessary (dependencies, data consistency, coordination complexity)
  • How you mitigate risk in either approach
  • A concrete example of each

STAR Method Answer Template

S
Situation

Describe the context - what was happening, what team/company, what was at stake

T
Task

What was your specific responsibility or challenge?

A
Action

What specific steps did you take? Be detailed about YOUR actions

R
Result

What was the outcome? Use metrics where possible. What did you learn?

💡 Tips

  • Default to phased when possible—it's usually lower risk
  • Acknowledge that sometimes big-bang is unavoidable; the key is having a solid rollback plan

✍️ Example Response

STAR format

Situation: At a payments company, we had to migrate our billing system to a new platform. The old system handled subscriptions for 2M customers; the new one had to support the same data model and APIs. We had a hard deadline—our vendor was sunsetting the legacy system in 14 months. The question was: phased migration by customer segment or a single cutover weekend?

Task: I was the engineering lead responsible for recommending the approach and then executing it. I had to weigh risk, complexity, and business constraints.

Action: I led an analysis of both options. Phased meant running two systems in parallel, dual-writes, and eventual cutover—more engineering work but lower risk. Big-bang meant one coordinated weekend with a full rollback plan—simpler technically but all-or-nothing. We had strong dependencies: billing tied to auth, entitlements, and reporting. A partial cutover would require those systems to support both old and new billing for months. I recommended phased by customer segment: we'd migrate enterprise customers first (smaller volume, more forgiving), then SMB, then consumer. Each phase had a 2-week validation window before we moved to the next. We built feature flags and a rollback script that could revert a segment in under 30 minutes. For our auth migration the year before, we'd done big-bang because the systems were tightly coupled and a phased approach would have doubled the timeline—there we invested heavily in rehearsals and a 4-hour rollback window.

Result: We completed the billing migration in 12 months with zero revenue-impacting incidents. One phase had a data sync issue; we rolled back in 20 minutes and fixed it before re-running. I learned that the right choice depends on coupling and timeline—phased when you can afford the complexity, big-bang when dependencies make it impractical, but always with a tested rollback plan.

🏢 Companies Known to Ask This

Company Variation / Focus
Amazon Deliver Results, Bias for Action — "Tell me about a time you made a trade-off under pressure"
Google Navigating ambiguity, technical judgment
Meta Moving fast, risk management
Microsoft Execution, customer focus
Stripe Technical growth, autonomy in complex rollouts
Uber Ownership culture, scaling systems

Cookie Preferences

Strictly Necessary
Required for the site to function. Cannot be disabled. Includes auth sessions and security tokens.
Always on
Analytics
Helps us understand how visitors use the site (page views, interactions). No personal data is sold.
Marketing
Used to show relevant ads and track campaign performance. Currently not used on this site.